Welcome to the Pipe Liners Podcast, Episode 321, sponsored by Inter-SYS Corporation, providers of points, the pipeline operations excellent management system, compliance and operations software for the Pipe Liners Control Center to address control, re-management, skater and audit readiness. Find out more about poems at intersyscorp.com. The Pipe Liners Podcast, where professionals, public eks and industry insiders share their knowledge and experience about technology, projects and pipeline operations. And now your host, Russell Treet.
Thanks for listening to the Pipe Liners Podcast. I appreciate you taking the time and to show that appreciation. We are giving away a customized Yeti Tumblr to one listener every episode. This week, our winner is Gary Winfrey with Enbridge.
Congratulations, Gary. You're Yeti's own sway. To learn how you can win this signature prize, stick around until the end of the episode. This week, we speak with Andre Schulz with SolarCraft about powering remote shutdown valves.
Andre, welcome to the Pipe Liners Podcast. Good day, Russell. How are you doing? I'm doing very well.
Very well. Thank you. Before we dive in, Andre, why don't you tell us a little bit about your background and what you do and how you found yourself in your current position at SolarCraft? Oh, it's a short story.
I started with SolarCraft about 12 years ago, currently I'm the technical director. I spend most of my time consulting with customers about what problems they have so we can apply our products for them. Started in this line of work about 20 years ago or so in South Africa, building solar power supplies and UPSs. I'm not enough for gas stations and vaccine fridges in the middle of nowhere.
Moved to the US, my wife is from you and ended up at SolarCraft where the business happens to be very similar. It was a shoe in. The things that we do on oil and gas pipelines is not that much different from powering motors and control systems outside of it. It's just a more fun application.
I think that we're learning a lot about DC power and solar power and battery banks and all that type of thing. But it's very different when you start powering motors. I'm a sell boat guy. There's a big difference between running your lights and your refrigeration because the refrigeration on a boat has no motors or compressor with it really versus running your air conditioner on a boat.
It's a whole different challenge, if you will. That's a great tip for why I asked you to come on the episode and talk about powering remote shutdown valves. Let me start by asking you, what are some of the key challenges in powering remote shutdown valves? What are some of the key problems that operators are trying to address and deal with?
That's a good question. When you lay a big fat pipeline through the middle of nowhere, the primary concern in the beginning is right away and where's the pipe crossing, rivers and where you're going with it and all the challenges with that. By the time people start laying in the pipe, they very often delay the consideration of how that's where you need valve actuators or measuring stations or things like that. It's frequently an issue that people go, okay, here's the location where a shutdown valve will be.
Let's phone the local power supply company and let them give us a rundown of what it will take to power our stuff. It gets harder and harder these days to do that. The valves are often three-phase, 180-volt or some high-powered single-phase devices. You then have to sit and wait a year or so until they can finally get round and lay line power over the heels which has its own right-of-way concerns.
Then they charge you an arm and a leg for that connection where they won't gather any revenue from the power that you consume, which you bend too little of it. Now you consider, let's put nitrogen out there and run maybe nitrogen or pressure-operated valve actuators. Those come with a slew of extra concerns and maintenance issues where anybody who has run at Christmas Eve with more nitrogen bottles in the snow over two sides will tell you it's not a very viable solution. Line gas on gas lines is a reliable solution but it's becoming increasingly more difficult to do that because there are very stringent emissions or regulations.
No, to that point, Andre, there's a huge rule making that's working its way through PHMSA right now that people are referring to as leak detection and repair. But it's really a methane emissions reduction rule. For all of these guys that are operating the natural gas line pressure valves, and there are a lot of them because they're highly reliable and very affordable, they're all going to have to be looking for a different way to actuate those valves. And many of those valves are in very remote areas with no power anywhere close.
That's a big deal for sure. That's right. I mean, your problems are compounded. It's a liquid line.
And then you said, how do you pressurize this business then? Yeah. Well, your comment about nitrogen bottles, I don't know if you have this experience but I certainly do. I have more than one occasion.
I've been working with a control center where they were trying to shut something down and the valve, even though everything looked good on the nitrogen bottles when they actually tried to crank the valve, they might get it started but they didn't get it completed. Yes. Because you might have all the pressure you need but you might not have, you might need three but nitrogen bottles to completely move the valve and only one of them is good. Right.
And you don't know. So it's problematic for sure. Right. What do you think the solution is?
I mean, obviously, SolarCraft is a solar power company. I can probably ought to start by talking about how you do it in a more simple case where you have a DC actuated valve. So a smaller valve, lower horsepower, that sort of thing. What are the considerations and issues for having a reliable system just to operate a DC actuator?
You can see what you mean. You know, a very good analogy would be something like an axis gate at a farm, right? Where you'll see a solar panel off to the side and there's a battery and there's somewhere in a box. There are two considerations with that gate.
It is assumed that the gate is not opening and closing and opening and closing all the time. It's occasional. So the first consideration would be how much power does it take to get that gate moving? How much power does it take while it's swinging and how long did it swing for?
The second consideration would be how often is that going to happen? Is this a busy gate where there's 20 people living and they go in and out the whole time? I mean, there's gates, right? Could be anything.
Or is this just a remote gate on the side of the farm and once a week somebody goes there? That would determine the size of the battery that's in there and the size of the solar panel, but it wouldn't really change the size of that DC motor. The secondary consideration is how much energy on average does it take to operate the control system? The thing that sits there listening for the remote that the farmer has depressed, the little red light that's on keeping the radio going, keeping the thing on freezing in wind.
So in that regard, a valve station, let's take for instance a 12-inch liquids line. The same considerations count. If it's a remote control shutdown actuated like an emergency shutdown, you can expect that actuated to run maybe once a year. Let's say once every six months when people do a partial stroke test or something.
It'll run at its most while they commission the thing. They may test the limits, run it left and right 10, 20 times or so. But after that, when everybody leaves and that settles, once every six months or so is typical. So we would then consider how much power does it take to get that valve swinging, while swinging, turning.
How much does it take to keep it running for the two or three minutes that it takes to get the job done? And then secondarily, how much energy on average do we have to spend on the telemetry, the BLC at the site because you're also going to be measured. Some pressures, some flow rates, people are analyzing. So those are continuous loads.
They are occasional loads and they are continuous loads. Well, those loads for the instruments and the BLC and all that are relatively small. That's right. Although they're continuous, but they're small versus the load for the actuator is large, but for a short period of time.
Yeah. So I would assume that one of the other considerations where you have a situation where you're operating an actuator, particularly on a shutdown valve that doesn't operate frequently, is how quickly can I recharge the batteries or how even quickly do I need to recharge the batteries? Because I could afford with a battery bank for emergency shutdown. I could probably afford to run those batteries almost all the way down and then take some time a day to get them recharged back up before I need to open the valve back.
Obviously that's not to be engineered and understood, but that dynamic for anybody that works with solar systems or remote power, they understand that dynamic is quite different than managing a base load for a set of electronics. That's right. We run the electronic load and the motor load in our solar motor UPS is from the same battery bank. So typically we want our system if some catastrophic event happens like somebody steals the solar array, you want the system to still at least be able to stay up about a week, maybe five days or a week or so.
Maybe enough and counter intuitively, one stroke of the actuator in any direction will consume maybe about two percent of the capacity of that battery bank, no more. Very large actuators, maybe five. So we would say put something like 800 amp hour, putting an amp hour battery bank at a site. Now that's blowing my mind a little bit, Andre, because having done this in the past, it's sometimes set down and done the math and tried to size batteries for a remote control panel.
But the idea of over sizing the batteries to that level, that's a little different than what I was doing at 10 plus years ago. But I guess given where batteries are and what's happening with lithium and the price points, that's a more affordable thing to do and it certainly goes to reliability. Oh, it absolutely does. So if you're drawing 100 watts for your control system to keep a couple of radios in the network switch and a PLC going.
It's two and a half kilowatt hours a day. If you run arguments like a two and a half kilowatt motor, but you only run it for three minutes every six months, how many kilowatt hours did you burn in the three minutes? You can do the calculation offline, but it's very little. The consideration with the actuator is not the amount of energy that you have to store.
Can you deliver the lock rotor current reliably out of the set of batteries? The capacity of the batteries is not the primary concern. For people who are listening, it's engineers a lot that listen to this, but I should probably decode something you just said. I had to when we were getting ready for this podcast, but lock rotor current, that was a new term for me.
Basically, that's the surge in current necessary to get the motor moving. Exactly. Starting to moving and that's a very short term, but very high spike in power requirement. That's right.
The draw is very large. The challenge with powering induction motors through say three-phase 480-volt, pick a number. Some battery banks is reliability. Many people will attend to do this with commercial or consumer grade equipment that's available, but they will disappoint you on short order.
Cellocrafts as developed. Before you go there, tell me a little bit about why that's so. Why will commercial off the shelf not get the job done? What's missing in that equipment?
Something like UPS's inverters that you can buy, generally they are designed with the first thing that power is a rectifier or a resistive load. When you power your television, the very first thing that happens to the AC power coming in is it gets converted to DC, right there. Most electronics are like that, certainly computer, UPS's are like that. UPS's in server rooms, you get very large ones, but their loads are almost entirely rectified.
Once they are that size, tiny things like say a refrigerator or some such will work just fine from them. A thing like a coffee machine for some consumer grade, UPS wouldn't be a challenge because it's almost entirely a resistive load to boil water, but a tiny motor load that can handle easily. I guess the point you're making is the nature of the load is critical to understanding how to design a system. Commercial stuff is more designed for resistive loads, not inductive loads.
That's right. That first spike, an energizing motor, energizing transformers, and the lockroker current of a motor is incredibly hard on such converting equipment. To do it so that you can install this system, but 20 years later, it's still running reliably, takes some doing. We have spent millions of R&D, devised what we call our ultra drive, which is the correct thing for this application.
I want to talk a little bit about that. Just on the surface of it, the idea of using solar to power a 480 volt, three-phase motor in the field in a remote application. I could see doing it as a backup to AC power maybe, but to have it be primary. Just on the surface of that, that seems inherently risky and problematic.
I guess you've laid out why people have had a lot of problems doing this because they're using commercial off-the-shelf system that just doesn't have the survivability or the life usage that's necessary for this application. This is something that needs to be industrially hardened and built for purpose. That's right. You spend a lot of time thinking and a lot of money paying the guy who thinks to think about heat mitigation and materials.
Once you've covered that, the reliability of the conversion, the next thing you look at is how do you make sure that this battery bank is always full? At that stage, it's not that much different from a UPS or a field UPS such as we make anymore. We know when we deploy these units exactly where they will be used. It's part of the initial series of questions we are.
What are these locations? Every one of these locations, in every subcode in the country, there's little weather stations everywhere. Part of them is what they call a pyronometer that records what does the solar resource look and how did it look like over the last 15 or 20 years. Then we look at how bad did it get.
We assume that such an apocalyptically dark event will occur again and then we size our solar array to be able to survive that. It's typically in the middle of winter. That's the time when it's called the sun is low on the horizon. It's always hazy and some such.
And then we make sure that the size of our battery bank and the size of our solar array is correct for it. You will also be surprised to find that the size of the solar array doesn't really have that much to do with the size of the actuator. As more to do with how often it operates. If you have to run it 20 times a day, now we're draining things and we have to put up bigger collective.
But on a shutdown valve, just about all the power, 90% of it is consumed by the telemetry, the PLC gadget tree. That's also kind of interesting because that's counterintuitive to me. It would seem like if I've got a 480-volt three-phase motor and I'm going to power it off of the 12-volt DC battery bank, just intuitively, it would seem like I'm going to need a lot of solar. I'm going to need a lot of battery to do that.
What you're telling me is no, you don't. What you need is a properly designed set of electronics that provides that power in the right way. That's right. And that's a different way of thinking about it, right?
It's a very different way of thinking about it. It's easy to get that wrong if it's the first time you do it. Yeah. Yeah.
That makes it right. Yeah. By now I just do it for a living. A lot of thumbs on the wall, right?
Yeah. Well, and this is a domain too, Andre, we're technologies evolving very quickly. The capabilities of the batteries, what we're finding in the rectifiers and the charging systems and the solar panels themselves, I mean, they're all that stuff's improving and it's improving quickly. Yeah.
So, if you haven't worked in this domain, like me for 10 years, is a lot that's different. Oh, there's a lot that's... Yeah, you've got to catch up. I mean, a casey point is, say, lithium batteries these days.
It's wonderful, amazing technology and you'd think that that's what you'd have to use then. However, we have issues with it. Number one, we kind of need the weight. We also need to be able to operate when it's minus 20 outside, which is a problem.
We take for short periods of time just enormous currents out of these batteries, which lithium batteries struggle with because they're BMS as we streak the stuff to keep their things reliable. So, in that regard, yes, we watch another technology growing outside of the field we're useless for. However, when it comes to the power conversion that we do from DC to the three-phase AC for the actuators, that is cutting edge. And we always have one or two engineers constantly working on improving the units getting the efficiency better, getting the reliability up.
What do you do if some of the components are not available anymore because there's a net factory shutdown? Do you have the next alternatives loaded so you don't have a gap in your product delivery? Things like that develop so fast that you've got to dance to keep up. Yeah, well, that's why I do the podcast because I'm helping people to keep up.
So, how do you address the reliability issue? I mean, a couple of takeaways from me from this. One is these systems need to be engineered for purpose. Another is that there's some unique and kind of proprietary technology that you guys have that is delivering the high voltage, multi-phase power for actuators, which makes sense to me why that would be important.
What else should somebody be aware of from a reliability standpoint? Oh, how do you kind of insure? Because the thing about a shutdown was I don't use it very often, but when I need them, I need them to work. Yes, got to be there.
Can I just fail? Developing the technology and the hardware in modules is done. That's a process on its own way. Yes, you want to use the best people and the best equipment.
Where people very often fall on their face when building a system that's reliable is they don't gather enough information or they don't spend the right amount of time making sure that the information that they have is correct. A good example is we put out a battery bank and a solar array size to support the site. That's very carefully calculated of what we think the continuous load will be. If we ask the customer, what do you think the continuous load from your telemetry and the PLC system will be?
He comes back with a number like 100 watt and we write down 100 watt and then we build our system like that. He may be wrong. It's important for us to go, how's that 100 watt built up? He goes, well, I got this radio over there, this network switch and then I've got this panel heater that we always use and you go, wait a minute.
You didn't mention the panel heater, but you said 100 watt. Let's delve into that. Getting the average power draw of the site, correct, is by far the biggest consideration with the reliability of the system. Very often somebody would put in a cell modem for the telemetry and somebody takes down that cell modem six months later and the company puts up a V-set that now burns easily 20 times more power than the cell modem.
It burns our battery bank. I wish I could say I've never seen that happen before. That's right. The other thing they'll do is they'll put the radio in and they'll say, well, I'm going to transmit every 15 minutes and then something will happen.
You know what I'm putting in leak detection, I need to transmit every 30 seconds. All of a sudden I just, you know, I just multiplied my power consumption by 20 fold and all I did was change the configuration of the software. Exactly. So what we do is we measure the design load and if you exceed the design load, we'll know or the customer will know they'll make an alarm in the telemetry, we'll save an analog input somewhere in the PLC that says if this design load increases beyond this number, some things happening over there.
You've got to know because this now jeopardizes the reliability of the system. That is absolutely by far the easiest way to make a site like this fail. You just have to know about it. As long as you measure for it, you alarm properly for it, you 90% redundancy in your battery banks is an issue, redundancy in your child's control is an issue.
Not using rubbish components. It burns me that it's absolutely always possible to make a system cheaper by using a crappier component that it's always possible to do that and it's always at the cost of uptime and reliability down the road. Well, there's also the cost associated with the maintenance, keeping it running when you know you've got to run out and replace bars. Well, let me tell you what I think my takeaways are.
This is really fascinating conversation for me. But here's my takeaways. First takeaway is the systems need to be designed and you need to very carefully and thoroughly consider what your design load is. That's the first thing.
The second thing is that you actually can power these high voltage multi-phase devices with solar, but you've got to have the right electronics designed for the right kind of load for that to work well. And then the other key takeaway is reliability starts with design and ends with monitoring consumption versus the design. Because the minute my consumption goes beyond what I designed for, I need to investigate what's going on there. So how do you think I did in terms of takeaways from this conversation?
Three out of three, sir. Great. Well, so as the listeners know, we will put together show notes and we'll build some links into the website page for this episode. If you guys want to know more about what SolarCraft is doing with powering remote shutdown valves, if you're trying to do methane mitigation, if you're trying to look for alternatives for power, I'd recommend you get touched with these guys.
So, Andre, thanks for your time. I appreciate it. You're most welcome. I hope you enjoyed this week's episode of the Pipeminers Podcast and our conversation with Andre.
Just a reminder before you go, you should register to win our customized Pipeminers Podcast Jiddy Tumblr. Simply visit pipeminepodcastnetwork.com and in yourself in the drawing. If you'd like to support this podcast, please leave us a review and you can do that on Apple Podcast, Google Play, Spotify, wherever you listen and you can find instructions at pipeminepodcastnetwork.com. If you have ideas, questions or topics you'd be interested in, please let me know on the contact us page at pipeminepodcastnetwork.com or reach out to me on LinkedIn.
Thanks for listening. I'll talk to you next week.